Docket Detail
| Docket 2012-225-E | |
| Opened On | Monday, June 4, 2012 |
|---|---|
| Status | Open |
| Industry | Electric |
| Summary | Application of South Carolina Electric & Gas Company for a Certificate of Environmental Compatibility and Public Convenience and Necessity for the Construction and Operation of Two 230 kV Transmission Lines from Its V.C. Summer Switchyard #2 to Its Planned St. George 230 kV Switching Station |
| Applicants (expand) | ||
| Total: 1 |
| Representatives (expand) | ||
| Total: 6 |
| Intervenors (expand) | ||
| Total: 4 |
| Protestants (expand) | ||
| Total: 1 |
| Matters Sortable Matter Listing | ||||
| MatterID | Type | Summary | Date | PDF(s) |
| 239154 | Directive |
Application of South Carolina Electric & Gas Company for a Certificate of Environmental Compatibility and Public Convenience and Necessity for the Construction and Operation of Two 230 kV Transmission Lines from Its V.C. Summer Switchyard #2 to Its Planned St. George 230 kV Switching Station - Commission Directive - Agenda Item 11 - This Matter is Ready for Final Disposition On behalf of: Clerk's Office |
9/12/2012 |
Directive |
| 238878 | Response |
Application of South Carolina Electric & Gas Company for a Certificate of Environmental Compatibility and Public Convenience and Necessity for the Construction and Operation of Two 230 kV Transmission Lines from Its V.C. Summer Switchyard #2 to Its Planned St. George 230 kV Switching Station - Response to Mr. Joseph's Wojcicki's Email of August 27, 2012 On behalf of: Public Service Commission |
9/4/2012 |
Response |
| 238785 | Proposed Order |
Application of South Carolina Electric & Gas Company for a Certificate of Environmental Compatibility and Public Convenience and Necessity for the Construction and Operation of Two 230 kV Transmission Lines from Its V.C. Summer Switchyard #2 to Its Planned St. George 230 kV Switching Station - Joint Proposed Order On behalf of: Office of Regulatory Staff |
8/30/2012 |
Cover Letter Joint Proposed Order + CoS |
| 238877 | General Matter |
Application of South Carolina Electric & Gas Company for a Certificate of Environmental Compatibility and Public Convenience and Necessity for the Construction and Operation of Two 230 kV Transmission Lines from Its V.C. Summer Switchyard #2 to Its Planned St. George 230 kV Switching Station - Email Correspondence Dated August 27, 2012 On behalf of: Joseph Wojcicki |
8/27/2012 |
Email |
| 238298 | Stipulation |
Application of South Carolina Electric & Gas Company for a Certificate of Environmental Compatibility and Public Convenience and Necessity for the Construction and Operation of Two 230 kV Transmission Lines from Its V.C. Summer Switchyard #2 to Its Planned St. George 230 kV Switching Station - Stipulation On behalf of: Office of Regulatory Staff and South Carolina Electric & Gas Company |
8/14/2012 |
Stipulation CoS |
| 238285 | Protestant |
Application of South Carolina Electric & Gas Company for a Certificate of Environmental Compatibility and Public Convenience and Necessity for the Construction and Operation of Two 230 kV Transmission Lines from Its V.C. Summer Switchyard #2 to Its Planned St. George 230 kV Switching Station - Protest and Request to Reserve Up to Thirty Minutes to Speak On behalf of: Joseph Wojcicki |
8/13/2012 |
Protest |
| 238121 | Testimony |
Application of South Carolina Electric & Gas Company for a Certificate of Environmental Compatibility and Public Convenience and Necessity for the Construction and Operation of Two 230 kV Transmission Lines from Its V.C. Summer Switchyard #2 to Its Planned St. George 230 kV Switching Station - Direct Testimony of Michael L. Seaman-Huynh On behalf of: Office of Regulatory Staff |
8/1/2012 |
Direct Testimony of MSH CoS |
| 237775 | Testimony |
Application of South Carolina Electric & Gas Company for a Certificate of Environmental Compatibility and Public Convenience and Necessity for the Construction and Operation of Two 230 kV Transmission Lines from Its V.C. Summer Switchyard #2 to Its Planned St. George 230 kV Switching Station - Direct Testimony and Exhibits of Hubert C. Young, III On behalf of: South Carolina Electric & Gas Company |
7/18/2012 |
Scanned Matter |
| 237776 | Testimony |
Application of South Carolina Electric & Gas Company for a Certificate of Environmental Compatibility and Public Convenience and Necessity for the Construction and Operation of Two 230 kV Transmission Lines from Its V.C. Summer Switchyard #2 to Its Planned St. George 230 kV Switching Station - Direct Testimony and Exhibits of Dwight M. Hollifield (Exhibit Available for Viewing at the Commission) On behalf of: South Carolina Electric & Gas Company |
7/18/2012 |
Scanned Matter |
| 237710 | Publisher's Affidavit |
Application of South Carolina Electric & Gas Company for a Certificate of Environmental Compatibility and Public Convenience and Necessity for the Construction and Operation of Two 230 kV Transmission Lines from Its V.C. Summer Switchyard #2 to Its Planned St. George 230 kV Switching Station - Proof of Publication Posted in The State Media Company, Incorporated in Richland County, The Time and Democrat in Orangeburg County and The Post and Courier in Charleston County Newspaper On behalf of: South Carolina Electric & Gas Company |
7/13/2012 |
Scanned Matter |
| 237138 | Notice |
Application of South Carolina Electric & Gas Company for a Certificate of Environmental Compatibility and Public Convenience and Necessity for the Construction and Operation of Two 230 kV Transmission Lines from Its V.C. Summer Switchyard #2 to Its Planned St. George 230 kV Switching Station - Notice of Filing and Hearing On behalf of: Clerk's Office |
6/13/2012 |
Notice |
| 237139 | Prefile Testimony Letter |
Application of South Carolina Electric & Gas Company for a Certificate of Environmental Compatibility and Public Convenience and Necessity for the Construction and Operation of Two 230 kV Transmission Lines from Its V.C. Summer Switchyard #2 to Its Planned St. George 230 kV Switching Station - Prefile Testimony Letter On behalf of: Clerk's Office |
6/13/2012 |
Prefile Testimony Letter |
| 237140 | Transmittal Letter |
Application of South Carolina Electric & Gas Company for a Certificate of Environmental Compatibility and Public Convenience and Necessity for the Construction and Operation of Two 230 kV Transmission Lines from Its V.C. Summer Switchyard #2 to Its Planned St. George 230 kV Switching Station - Transmittal Letter On behalf of: Clerk's Office |
6/13/2012 |
Transmittal Letter |
| 237077 | General Matter |
Application of South Carolina Electric & Gas Company for a Certificate of Environmental Compatibility and Public Convenience and Necessity for the Construction and Operation of Two 230 kV Transmission Lines from Its V.C. Summer Switchyard #2 to Its Planned St. George 230 kV Switching Station - Notice of Appearance of Counsel - Jeffrey M. Nelson On behalf of: Office of Regulatory Staff |
6/7/2012 |
NOA |
| 237003 | Application |
Application of South Carolina Electric & Gas Company for a Certificate of Environmental Compatibility and Public Convenience and Necessity for the Construction and Operation of Two 230 kV Transmission Lines from Its V.C. Summer Switchyard #2 to Its Planned St. George 230 kV Switching Station On behalf of: South Carolina Electric & Gas Company |
6/1/2012 |
Exhibit_A Exhibit_A_Figures_Part2 Exhibit_A_Apendix_A-F Exhibit_A_Apendix_G Exhibit_A_Apendix_I-K Application Exhibit_A_Figures_Part1 Exhibit_A_Apendix_H |
| Orders | |||
| Order# | Summary | Date | PDF(s) |
| 2012-730 | Order Granting a Certificate of Environmental Compatibility and Public Convenience and Necessity - Application of South Carolina Electric & Gas Company for a Certificate of Environmental Compatibility and Public Convenience and Necessity for the Construction and Operation of Two 230 kV Transmission Lines from Its V.C. Summer Switchyard #2 to Its Planned St. George 230 kV Switching Station | 9/26/2012 |
Order Number 2012-730 |
| Timeline | |
| Event | Date |
| Application Received | 6/1/12 |
| Issue Final Order | |
| Proof Pub Due For Merits Hearing | |
| Return Date | 7/16/12 |
| Applicant/Complainant/Petitioner Testimony Due | 7/18/12 |
| All Other Parties Due Date | 8/1/12 |
| Rebuttal Testimony Due Date | 8/8/12 |
| Surrebuttal Testimony Due Date | 8/15/12 |
| Hearings | ||
| Date | Status | Notes |
| Wednesday, August 22, 2012 @ 10:30 AM | Scheduled | |